Microsoft
74-343 · Question #69
74-343 Question #69: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #69. The question stem and answer options stay visible for context.
Question
You are a project manager who uses Project Professional 2013. You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks. You need to monitor this phase closely to ensure that it does not overrun. What should you do?
Options
- ACreate an automatically scheduled summary task of 20 days.
- BCreate a manually scheduled summary task of 20 days.
- CCreate a manually scheduled summary task of 20 days.
- DCreate an automatically scheduled summary task of 20 days.
- ESet a deadline date for the automatically scheduled summary task for four weeks after July 1.
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.