74-343 · Question #69
You are a project manager who uses Project Professional 2013. You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to…
The correct answer is E. Set a deadline date for the automatically scheduled summary task for four weeks after July 1. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Professional 2013. You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks. You need to monitor this phase closely to ensure that it does not overrun. What should you do?
Options
- ACreate an automatically scheduled summary task of 20 days.
- BCreate a manually scheduled summary task of 20 days.
- CCreate a manually scheduled summary task of 20 days.
- DCreate an automatically scheduled summary task of 20 days.
- ESet a deadline date for the automatically scheduled summary task for four weeks after July 1.
How the community answered
(20 responses)- B10% (2)
- C5% (1)
- E85% (17)