You are a project manager who uses Project Professional 2013. You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to…

The correct answer is E. Set a deadline date for the automatically scheduled summary task for four weeks after July 1. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks. You need to monitor this phase closely to ensure that it does not overrun. What should you do?

Options

  • ACreate an automatically scheduled summary task of 20 days.
  • BCreate a manually scheduled summary task of 20 days.
  • CCreate a manually scheduled summary task of 20 days.
  • DCreate an automatically scheduled summary task of 20 days.
  • ESet a deadline date for the automatically scheduled summary task for four weeks after July 1.

How the community answered

(20 responses)
  • B
    10% (2)
  • C
    5% (1)
  • E
    85% (17)

Community Discussion

No community discussion yet for this question.