Microsoft
74-343 · Question #68
You are a project manager for a company that uses Project Professional 2013. You are developing a schedule and plan to use the leveling order of Priority, Standard. You need to create a task which…
The correct answer is B. Set task priority to 1000. See the full explanation below for the reasoning.
Question
You are a project manager for a company that uses Project Professional 2013. You are developing a schedule and plan to use the leveling order of Priority, Standard. You need to create a task which leveling will not change. What should you do?
Options
- ASet task priority to 100
- BSet task priority to 1000
- CSet task priority to 0
- DSet task priority to 1
How the community answered
(27 responses)- A15% (4)
- B74% (20)
- C7% (2)
- D4% (1)
Community Discussion
No community discussion yet for this question.