You are a project manager for a company that uses Project Professional 2013. You are developing a schedule and plan to use the leveling order of Priority, Standard. You need to create a task which leveling will not change. What should you do?
Options
- ASet task priority to 100
- BSet task priority to 1000
- CSet task priority to 0
- DSet task priority to 1
Unlock 74-343 to see the answer