Question

You are a project manager for a company that uses Project Professional 2013. You are developing a schedule and plan to use the leveling order of Priority, Standard. You need to create a task which leveling will not change. What should you do?

Options

  • ASet task priority to 100
  • BSet task priority to 1000
  • CSet task priority to 0
  • DSet task priority to 1