Question
Your company uses Project Professional 2013. You have several projects that are part of a program, but you do not use Project Server. You use a Resource Pool file to share resources across all projects. You are informed that one of the projects is cancelled before it starts. As a result, you need to delete the project. What happens in the resource pool after you delete the project?
Options
- AThe resource pool will still reflect the resource needs of the deleted project.
- BThe resource pool will prompt that the project is deleted the next time it is opened, allowing
- CThe resource pool is automatically updated when you delete the project.
- DThe resource pool will still reflect the resource needs of the deleted project.
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.