74-343 · Question #103
While creating a schedule with Project Professional 2013, you notice that there is a three-day duration on the Database Design task. After working for only two days, the resource performing the task…
The correct answer is B. Add two days of actual duration and change the remaining duration for the task to zero. See the full explanation below for the reasoning.
Question
While creating a schedule with Project Professional 2013, you notice that there is a three-day duration on the Database Design task. After working for only two days, the resource performing the task reports two days of work and notifies you that the task is finished. You need to update the schedule with this information. What should you do?
Options
- AReschedule uncompleted work for the project schedule.
- BAdd two days of actual duration and change the remaining duration for the task to zero.
- CUpdate the task to show 100% completion on the ribbon bar.
- DEnter a status date for the task.
How the community answered
(44 responses)- A2% (1)
- B82% (36)
- C11% (5)
- D5% (2)