74-343 · Question #101

You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have…

The correct answer is C. Enter the availability start and end dates for each resource and change the working time for. See the full explanation below for the reasoning.

Question

You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability. You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours. What should you do?

Options

  • AChange the part-time resources' tasks to manually scheduled to ensure the dates do not go
  • BEnter the availability start and end dates for each resource and change the percent of units
  • CEnter the availability start and end dates for each resource and change the working time for
  • DChange the part-time resources' units to the percentage they are available and set task

How the community answered

(58 responses)
  • A
    7% (4)
  • B
    14% (8)
  • C
    76% (44)
  • D
    3% (2)