Question
You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability. You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours. What should you do?
Options
- AChange the part-time resources' tasks to manually scheduled to ensure the dates do not go
- BEnter the availability start and end dates for each resource and change the percent of units
- CEnter the availability start and end dates for each resource and change the working time for
- DChange the part-time resources' units to the percentage they are available and set task