nerdexam
Microsoft

74-343 · Question #101

74-343 Question #101: Real Exam Question with Answer & Explanation

Sign in or unlock 74-343 to reveal the answer and full explanation for question #101. The question stem and answer options stay visible for context.

Question

You are a senior project manager, and your organization uses Project Standard 2013. You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability. You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours. What should you do?

Options

  • AChange the part-time resources' tasks to manually scheduled to ensure the dates do not go
  • BEnter the availability start and end dates for each resource and change the percent of units
  • CEnter the availability start and end dates for each resource and change the working time for
  • DChange the part-time resources' units to the percentage they are available and set task

Unlock 74-343 to see the answer

You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 74-343 Practice