Microsoft
74-343 · Question #100
74-343 Question #100: Real Exam Question with Answer & Explanation
The correct answer is A. Right-click the task and reassign it to the underallocated resource.. See the full explanation below for the reasoning.
Question
You are a project manager, and your organization uses Project Professional 2013. You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated. You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set. What should you do?
Options
- ARight-click the task and reassign it to the underallocated resource.
- BDrag the underallocated resource on the task to reassign it.
- CDrag one of the tasks from the overallocated resource to the Unassigned Tasks section.
- DRight-click the resource and reassign it to the underallocated resource.
Community Discussion
No community discussion yet for this question.