74-343 · Question #104

74-343 Question #104: Real Exam Question with Answer & Explanation

The correct answer is D. Use the Task path function to check driven successors for the Develop Software Delivery. See the full explanation below for the reasoning.

Question

You use Project Professional 2013 to manage a project schedule which includes all task relationships. The resource who is assigned to the "Develop software delivery" task is no longer available to work on your project. You can find another resource to perform this task, but you are not sure when the resource will become available. You need to know which future tasks could be affected as a result of the resource leaving your project. What should you do?

Options

  • ASort all tasks by start date and check start dates of tasks that are scheduled after the Develop
  • BView the critical path for tasks that are successors to the Develop Software Delivery task.
  • CView the Network diagram and filter for the predecessor tasks to Develop Software Delivery
  • DUse the Task path function to check driven successors for the Develop Software Delivery