You need to create a project plan that accommodates the corporate holiday calendar. What should you do?

The correct answer is A. Add exceptions to the project calendar for corporate holidays. See the full explanation below for the reasoning.

Question

You need to create a project plan that accommodates the corporate holiday calendar. What should you do?

Options

  • AAdd exceptions to the project calendar for corporate holidays.
  • BCreate an interim plan that includes the defined holidays to track the holidays.
  • CCreate a task for each holiday and assign each resource to each holiday task.
  • DAdjust the maximum units for each resource to reflect the total working days for the year.

How the community answered

(31 responses)
  • A
    71% (22)
  • B
    3% (1)
  • C
    19% (6)
  • D
    6% (2)