Question

You need to create a project plan that accommodates the corporate holiday calendar. What should you do?

Options

  • AAdd exceptions to the project calendar for corporate holidays.
  • BCreate an interim plan that includes the defined holidays to track the holidays.
  • CCreate a task for each holiday and assign each resource to each holiday task.
  • DAdjust the maximum units for each resource to reflect the total working days for the year.