nerdexam
Microsoft

70-178 · Question #14

You use Project Professional 2010 to manage a construction project. Different members of the project team frequently modify a blueprint file. The file is saved in a Microsoft Office SharePoint…

The correct answer is A. Add a hyperlink. See the full explanation below for the reasoning.

Question

You use Project Professional 2010 to manage a construction project. Different members of the project team frequently modify a blueprint file. The file is saved in a Microsoft Office SharePoint document library. You need to access the file from within the project schedule. What should you do?

Options

  • AAdd a hyperlink.
  • BUse the Links Between Projects tool.
  • CUse the Sync with Tasks List feature.
  • DUse the Save to SharePoint feature.

How the community answered

(60 responses)
  • A
    80% (48)
  • B
    10% (6)
  • C
    3% (2)
  • D
    7% (4)

Community Discussion

No community discussion yet for this question.

Full 70-178 Practice