A program manager learns that their company's organizational strategy has changed. This change impacts one component project of a program misaligning it with both the program objectives and the new…

The correct answer is B. Assess the impact of closure on other component projects, and generate a recommendation for. See the full explanation below for the reasoning.

Program Governance

Question

A program manager learns that their company's organizational strategy has changed. This change impacts one component project of a program misaligning it with both the program objectives and the new organizational strategy. This component project, however, is already 90 percent complete. What should the program manager do next?

Options

  • AImmediately submit a component project closure request to the program sponsor so that
  • BAssess the impact of closure on other component projects, and generate a recommendation for
  • CRecommend that the component project manager complete work activity to deliver benefits to the
  • DUpdate the benefits management plan to reflect the impact of the change on the program and its

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    84% (26)
  • C
    3% (1)
  • D
    10% (3)

Topics

#strategic misalignment#component project closure#impact assessment#program governance