A program delivers incremental benefits but is far from closure. The company completes an acquisition and defines new strategic objectives. What should the program manager do next?

The correct answer is D. Review the benefits management plan to assess the continued validity of the program. See the full explanation below for the reasoning.

Strategic Program Management

Question

A program delivers incremental benefits but is far from closure. The company completes an acquisition and defines new strategic objectives. What should the program manager do next?

Options

  • AEvaluate the impact of the new strategic objectives through a change request
  • BIntegrate the new acquisition into the program to include the new strategic objectives
  • CAssess the impact of the new acquisition on the contract management plan
  • DReview the benefits management plan to assess the continued validity of the program

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    14% (6)
  • C
    7% (3)
  • D
    74% (31)

Topics

#strategic alignment#organizational acquisition#benefits management plan#program validity