RCDDV15 · Question #146

A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What…

The correct answer is C. Arrange a meeting with both sponsors and the steering committee to present the market analysis. See the full explanation below for the reasoning.

Program Governance

Question

A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?

Options

  • AFinalize the business case and market analysis with the cote program team and present the
  • BWork with the core program team to conduct a market analysis and make the decision based on
  • CArrange a meeting with both sponsors and the steering committee to present the market analysis
  • DEngage the program stakeholders present the market analysis and findings to facilitate the

How the community answered

(53 responses)
  • A
    17% (9)
  • B
    4% (2)
  • C
    70% (37)
  • D
    9% (5)

Topics

#sponsor conflict resolution#steering committee#stakeholder management#governance