The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?
The correct answer is C. Earned value management financial reporting systems, performance measurement techniques. See the full explanation below for the reasoning.
Program Governance
Question
The program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?
Options
- AProgram management performance variances business criteria reweighting, root cause
- BInterviewing, SWOT analysis, run chart and matrix-based charts
- CEarned value management financial reporting systems, performance measurement techniques
- DDelphi technique, scatter diagram. Pareto chart, and organization charts
How the community answered
(28 responses)- A4% (1)
- B4% (1)
- C79% (22)
- D14% (4)
Topics
#earned value management#performance monitoring#financial reporting systems#program control