A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this…
The correct answer is C. Assess the benefits and impact to the program. See the full explanation below for the reasoning.
Program Governance
Question
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue. What should the program manager do NEXT?
Options
- AConsider the option to close out the key project
- BEvaluate the program and re-baseline the objectives
- CAssess the benefits and impact to the program.
- DAmend the risk register with the key project changes
How the community answered
(26 responses)- A15% (4)
- B4% (1)
- C77% (20)
- D4% (1)
Topics
#change request#benefits impact assessment#program performance#component project issues