The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost…
The correct answer is B. Estimate at completion. See the full explanation below for the reasoning.
Program Governance
Question
The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle. Which of the following would the customer be interested in reviewing?
Options
- AEstimate to complete
- BEstimate at completion
- COriginal cost baseline
- DCost performance index
How the community answered
(44 responses)- A7% (3)
- B77% (34)
- C14% (6)
- D2% (1)
Topics
#estimate at completion#earned value management#cost performance#program reporting