The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost…

The correct answer is B. Estimate at completion. See the full explanation below for the reasoning.

Program Governance

Question

The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle. Which of the following would the customer be interested in reviewing?

Options

  • AEstimate to complete
  • BEstimate at completion
  • COriginal cost baseline
  • DCost performance index

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    77% (34)
  • C
    14% (6)
  • D
    2% (1)

Topics

#estimate at completion#earned value management#cost performance#program reporting