A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?
The correct answer is C. Update the program roadmap to reflect completion of a key end-point objective. See the full explanation below for the reasoning.
Program Life Cycle Management
Question
A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?
Options
- AUpdate the program stakeholder engagement plan with stakeholders from the transition
- BDefine the component protects business value in the benefits management plan
- CUpdate the program roadmap to reflect completion of a key end-point objective
- DInitiate a program change request to close out the component project
How the community answered
(52 responses)- A12% (6)
- B4% (2)
- C79% (41)
- D6% (3)
Topics
#program roadmap#component closure#incremental benefits#delivery phase transition