RCDD Exam Questions
371 real RCDD exam questions with expert-verified answers and explanations. Page 6 of 8.
- Question #251
You are designing an audible alarm notification system for an office environment with an ambient noise level of 55 dBA. What dBA level should the horn be set at?
- Question #252
You are designing a strobe visual notification system for a fire alarm system. You have a hallway that is 4.6 m (15 ft) wide and 100 m (328 ft) long. How many strobes should be pla...
- Question #253
An outside plant (OSP) cable must be placed under a pipeline with two side by side pipe runs. The distance between the outside pipes is 6 m (20 ft). What is the length of the condu...
- Question #254
All entrance conduits should be equipped with a plastic or nylon line with a MINIMUM test rating of _________ pulling tension.
- Question #255
You are placing an entrance cable between two buildings connected by a conduit 205.3 m (588 ft) in length. What would be the MAXIMUM length of unlisted OSP cable that could be used...
- Question #256
To reduce the chance of an accidental dig-up, plastic warning tape should be placed a MINIMUM of _________ below grade, but high enough above cables to allow detection before cable...
- Question #257
What is the MINIMUM number of outside building terminal pedestals required to serve a single story office, or office warehouse structure that has ten 18.3 m x 24 m (60 ft x 80 ft)...
- Question #258
What is the horizontal separation, in well tamped earth, required between power and direct buried telecommunications facilities sharing the same trench?
- Question #259
The MOST common medium used to provide service to the access point (AP) is ________ cable.
- Question #260
Which one of the following is NOT an advantage of direct-buried cable?
- Question #261
You have determined that your underground cable design requires three maintenance holes (MHs). One is 4.3 m (14 ft), one is 6 m (20 ft), and one is 6.7 m (22 ft) in length. How man...
- Question #262
The information technology system (ITS) designer should design conduits entering a building from ceiling height to terminate ________ below the finished ceiling.
- Question #263
Buildings larger than ________ must contain a dedicated room for the termination of entrance facilities.
- Question #264
What is the MINIMUM vertical separation between the top rail of a railroad track and telecommunications facilities placed beneath the track?
- Question #265
Aerial entrances to small buildings should be limited to ________ cable pair or less.
- Question #266
The information technology system (ITS) designer should design conduits entering a building from below grade point to extend ________ above finished floor (AFF).
- Question #267
You have the responsibility of designing a railroad track crossing for an outside plant OSP cable. There are three separate railroad tracks to be crossed. The measurement between t...
- Question #268
When selecting poles for aerial telecommunications facilities, which of the following is the class number for the strongest rated pole?
- Question #269
What is the MINIMUM cover for underground conduit?
- Question #270
BICSI recommends that any trench ________ or more deep must be shored to prevent cave in.
- Question #271
When a building is not on the property line, the building owner should provide a MINIMUM of ________ conduits from a point inside the building, to the property line or easement for...
- Question #272
The MAXIMUM span length for an aerial entrance, from the last pole to the building, must NOT exceed:
- Question #273
Vertical conduit masts (with approved service heads) are limited to drop-wire attachments of up to ________ lines.
- Question #274
What warning tape color has the Common Ground Alliance (CGA) adopted for telecommunications and CATV cables?
- Question #275
Which one of the following is NOT an advantage of underground conduit?
- Question #276
When installing underground entrances, no more than ________ 90-degree bends should be included between pulling points.
- Question #277
Within a data center, how many concentric layers are considered necessary to provide effective security?
- Question #278
If you are working on a physical security plan for a data center and focusing on building and access control, what layer of the plan would this relate to?
- Question #279
What type of redundancy provides two additional units, modules, paths, or systems in addition to the MINIMUM required to satisfy the base requirement.
- Question #280
It is important to keep all underfloor cabling systems very neat and orderly. Cabling systems must be managed to ensure that air flow is not impeded by the height or volume of unde...
- Question #281
Within a data center, if you have dual path connectivity between the primary entrance room and secondary entrance room, in addition to dual connectivity between these two rooms and...
- Question #282
You have been asked to spec the physical security requirements related to the protection of assets for a new data center. The most common potential for damage categories you have c...
- Question #283
Within a data center, if you have a system which includes one extra unit, in addition to the minimum required to satisfy the base need, and where the failure of this unit will NOT...
- Question #284
What type of redundancy provides two complete units, modules, paths or systems for every one required for a base system.
- Question #285
What is the MAXIMUM horizontal cable length permitted for centralized optical fiber cabling from the MDA within a data center?
- Question #286
You are designing a cabling containment system installed overhead in a new data center. The main or prime purpose of the system will be to manage fiber optic cabling between cabine...
- Question #287
If you have a data center where the entire infrastructure must be completely shutdown on an annual basis to perform preventative maintenance and repair work, what tier level would...
- Question #288
What does ANSI/TIA 942 recommend as the MINIMUM height for overhead cable tray above finished floor within a data center?
- Question #289
If you have a 30 cm (12 in) wide data tray, what does ANSI/TIA 569-B recommend be the maximum pathway fill cross sectional area assuming a MAXIMUM pathway depth of 15 cm (6 in)?
- Question #290
You are renovating telecommunication rooms that support an acute care facility that has 10,000 sq ft floors. The facility will be adding 15,000 sq ft to each of the floors. What is...
- Question #291
You are designing a nurse call system for a health care facility. The system will have emergency call switches. What is the first step you should take in designing the nurse call s...
- Question #292
How much area of wall space is needed in the telecommunications room (TR) to support a nurse call system?
- Question #293
Which of the following is an alarm management output system?
- Question #294
Which of the following is used to create an electronic signal that can be sent to the central nurse call equipment?
- Question #295
You are designing a nurse call system for an assisted care facility. What type of nurse call system would best suit the needs for the facility?
- Question #296
The ________ system is an application used for storing and viewing captured digital radiology image files.
- Question #297
You are designing an interactive patient television system (IPTS) that will provide internet, nurse call and LCD television services. From the following, which medium will NOT supp...
- Question #298
In new construction, what is the percentage of pay phones that must be equipped with volume controls?
- Question #299
Coupling with electrical circuits can create inductive interference to telecommunications facilities. Which of the following can decrease the coupling effect?
- Question #300
In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?