nerdexam
BICSI

RCDD · Question #300

In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?

The correct answer is A. Installed one or two pair cables from the boat slips to a distribution terminal on the closest point of. For marina installations with fewer than 10 slips, the pre-cabling guideline for terminal A is to run one or two pair cables from each boat slip to a distribution terminal at the nearest accessible point on the dock.

Special Applications

Question

In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?

Exhibit

RCDD question #300 exhibit

Options

  • AInstalled one or two pair cables from the boat slips to a distribution terminal on the closest point of
  • BPlace distribution cable onto the dock and terminate in a suitable cabinet or enclosure.
  • CPre-cable each boat slip during construction.
  • DFor security, each install should be terminated in the patch panel/cross-connect at the dockmaster or

How the community answered

(26 responses)
  • A
    81% (21)
  • B
    4% (1)
  • C
    12% (3)
  • D
    4% (1)

Why each option

For marina installations with fewer than 10 slips, the pre-cabling guideline for terminal A is to run one or two pair cables from each boat slip to a distribution terminal at the nearest accessible point on the dock.

AInstalled one or two pair cables from the boat slips to a distribution terminal on the closest point ofCorrect

BICSI cabling guidelines for small marina installations with fewer than 10 slips specify installing one or two pair cables from each individual boat slip directly to a distribution terminal positioned at the closest accessible point, providing a simple point-to-distribution topology scaled for low-density deployments. This approach avoids the complexity and cost of larger backbone infrastructure while ensuring each slip has a dedicated connection path. The distribution terminal at the nearest point minimizes cable runs and serves as the aggregation node before connecting to the broader telecommunications system.

BPlace distribution cable onto the dock and terminate in a suitable cabinet or enclosure.

Placing distribution cable on the dock and terminating in a cabinet or enclosure describes a distribution architecture suited for larger marina installations, not the specific terminal A guideline for fewer than 10 slips.

CPre-cable each boat slip during construction.

Pre-cabling each slip during construction is a construction-phase activity that describes when to install cable, not the specific cabling topology or terminal A distribution guideline for small marinas.

DFor security, each install should be terminated in the patch panel/cross-connect at the dockmaster or

Terminating in a patch panel or cross-connect at the dockmaster office is a guideline applicable to larger or more complex marina deployments, not to the small-installation scenario described.

Concept tested: Marina pre-cabling guidelines for small slip installations

Topics

#marina cabling#pre-cabling#boat slips#distribution terminal

Community Discussion

No community discussion yet for this question.

Full RCDD Practice