All entrance conduits should be equipped with a plastic or nylon line with a MINIMUM test rating of _________ pulling tension.

The correct answer is D. 90 kg (200 lbs). Industry standards (per BICSI and related OSP installation guidelines) require that all entrance conduits be pre-installed with a pull line rated for a minimum pulling tension of 90 kg (200 lbs). This rating ensures the line is strong enough to pull entrance cables without…

Information Transport Systems (ITS) Distribution

Question

All entrance conduits should be equipped with a plastic or nylon line with a MINIMUM test rating of _________ pulling tension.

Options

  • A22.7 kg (50 lbs)
  • B45.4 kg (100 lbs)
  • C68 kg (150 lbs)
  • D90 kg (200 lbs)
  • E113 kg (250 lbs)

How the community answered

(53 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    2% (1)
  • D
    85% (45)
  • E
    8% (4)

Explanation

Industry standards (per BICSI and related OSP installation guidelines) require that all entrance conduits be pre-installed with a pull line rated for a minimum pulling tension of 90 kg (200 lbs). This rating ensures the line is strong enough to pull entrance cables without breaking during the pull, while also being compatible with the typical weight and friction loads encountered in entrance conduit runs. Pull lines rated below 90 kg (200 lbs) risk snapping under load, leaving the conduit inaccessible without re-boring or rodding.

Topics

#entrance conduit#pull line#pulling tension#conduit installation

Community Discussion

No community discussion yet for this question.