You have determined that your underground cable design requires three maintenance holes (MHs). One is 4.3 m (14 ft), one is 6 m (20 ft), and one is 6.7 m (22 ft) in length. How many MH covers are requ
The correct answer is D. Seven. The number of maintenance hole covers depends on the length of each MH per BICSI TDMM allocation rules, not simply one cover per MH.
Question
You have determined that your underground cable design requires three maintenance holes (MHs). One is 4.3 m (14 ft), one is 6 m (20 ft), and one is 6.7 m (22 ft) in length. How many MH covers are required to serve these MHs?
Options
- AThree
- BFour
- CSix
- DSeven
- ENine
How the community answered
(32 responses)- B6% (2)
- C3% (1)
- D78% (25)
- E13% (4)
Why each option
The number of maintenance hole covers depends on the length of each MH per BICSI TDMM allocation rules, not simply one cover per MH.
Three assumes one cover per MH regardless of length, which violates BICSI length-based cover allocation rules for MHs exceeding 15 ft.
Four undercounts because it does not account for the additional covers required for the 6.7m (22 ft) MH.
Six would only be correct if every MH required exactly two covers, but a 14 ft MH only requires one and a 22 ft MH requires four.
Per BICSI TDMM outside plant standards, MH cover allocation is length-dependent: a 4.3m (14 ft) MH requires 1 cover, a 6m (20 ft) MH requires 2 covers, and a 6.7m (22 ft) MH requires 4 covers, yielding a total of 7. The longer the MH, the more access covers are needed to meet safe entry and emergency egress requirements.
Nine overcounts the total; no combination of the three MH lengths produces a nine-cover requirement under BICSI standards.
Concept tested: Maintenance hole cover count by length