PSM-II · Question #88

Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on…

The correct answer is B. The Development Team members will write it as they are still responsible for creating the. All Product Backlog items selected for the Sprint are owned by the Development Team as a Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

Applying Scrum

Question

Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint. What should you do?

Options

  • AEncourage the technical writers from other teams to form a specialized team to organize and plan
  • BThe Development Team members will write it as they are still responsible for creating the
  • CWait until the technical writer returns before continuing with related items.
  • DComplete all development work first while adding technical documentation to the Product Backlog

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    83% (20)
  • C
    4% (1)
  • D
    8% (2)

Explanation

All Product Backlog items selected for the Sprint are owned by the Development Team as a Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

Topics

#Definition of Done#Development Team accountability#Sprint#cross-functionality