PSM-II · Question #89
PSM-II Question #89: Real Exam Question with Answer & Explanation
The correct answer is B. The Development Team is responsible because it is an internal team issue, and may request help. The ones closest to the problem are the best ones to understand and solve the problems. The Scrum Master can remove members (if empowered). The question is focused on the ownership of the root problem. The Development Team is responsible for addressing internal conflicts and may
Question
Options
- AThe Scrum Master because he/she is responsible for removing Impediments.
- BThe Development Team is responsible because it is an internal team issue, and may request help
- CThe HR department, as they are responsible for the hiring process.
- DThe Product Owner because he/she is responsible for managing the team.
Explanation
The ones closest to the problem are the best ones to understand and solve the problems. The Scrum Master can remove members (if empowered). The question is focused on the ownership of the root problem. The Development Team is responsible for addressing internal conflicts and may request help from the Scrum Master if needed. Because this is a localized issue, they are the ones that must initiate the actions for the results they desire.
Community Discussion