What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?

The correct answer is D. Inform the Product Owner so he/she can work with the person. Allow the Product Owner to decide what to do with the item as he/she is responsible for the flow

Applying Scrum

Question

What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?

Options

  • AAdd the item to the bottom of the Sprint Backlog.
  • BReplace an item in the current Sprint of equal size.
  • CAdd the item to the top of the next Sprint Backlog.
  • DInform the Product Owner so he/she can work with the person.

How the community answered

(26 responses)
  • A
    4% (1)
  • C
    4% (1)
  • D
    92% (24)

Explanation

Allow the Product Owner to decide what to do with the item as he/she is responsible for the flow

Topics

#Sprint scope#external requests#Product Owner#Development Team