PSM-II · Question #65
What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?
The correct answer is D. Inform the Product Owner so he/she can work with the person. Allow the Product Owner to decide what to do with the item as he/she is responsible for the flow
Applying Scrum
Question
What should the Development Team do if they are approached by someone outside the team and asked to add a "very important" item to a Sprint that is in progress?
Options
- AAdd the item to the bottom of the Sprint Backlog.
- BReplace an item in the current Sprint of equal size.
- CAdd the item to the top of the next Sprint Backlog.
- DInform the Product Owner so he/she can work with the person.
How the community answered
(26 responses)- A4% (1)
- C4% (1)
- D92% (24)
Explanation
Allow the Product Owner to decide what to do with the item as he/she is responsible for the flow
Topics
#Sprint scope#external requests#Product Owner#Development Team