Who manages the progress of work during a Sprint?

The correct answer is D. The Development Team. The Development Team is self-organized, thus manages and decides how to manage their own

Applying Scrum

Question

Who manages the progress of work during a Sprint?

Options

  • AThe Scrum Master
  • BThe Product Owner
  • CThe Team Lead
  • DThe Development Team

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    4% (1)
  • D
    88% (23)

Explanation

The Development Team is self-organized, thus manages and decides how to manage their own