PSM-II · Question #63
PSM-II Question #63: Real Exam Question with Answer & Explanation
The correct answer is D. Inform Peter that the projected completion date is not correct. The Development team would. See the full explanation below for the reasoning.
Question
Peter is a new Product Owner on a newly formed Scrum Team. Peter has projected a product completion date based on an estimated velocity of 21 completed points per Sprint. After the first 3 Sprints, the team has determined that their maximum velocity is 15 points and they are unable to create shippable increments at the end of each Sprint. What is the best way to proceed?
Options
- AThe Sprints have failed to produce shippable Increments there for opportunities to inspect and
- BThe Scrum Master would coach the team on improving their estimations and commitment to
- CExtend the Sprint in order to complete the Sprint Backlog items.
- DInform Peter that the projected completion date is not correct. The Development team would
Community Discussion
No community discussion yet for this question.