PSM-II · Question #63

Peter is a new Product Owner on a newly formed Scrum Team. Peter has projected a product completion date based on an estimated velocity of 21 completed points per Sprint. After the first 3 Sprints…

The correct answer is D. Inform Peter that the projected completion date is not correct. The Development team would. Option D is correct because Scrum is built on transparency and empiricism - when actual velocity (15 points) differs significantly from the projection (21 points), the Product Owner has an obligation to update stakeholders with a revised completion date based on real data, not…

Coaching & Mentoring

Question

Peter is a new Product Owner on a newly formed Scrum Team. Peter has projected a product completion date based on an estimated velocity of 21 completed points per Sprint. After the first 3 Sprints, the team has determined that their maximum velocity is 15 points and they are unable to create shippable increments at the end of each Sprint. What is the best way to proceed?

Options

  • AThe Sprints have failed to produce shippable Increments there for opportunities to inspect and
  • BThe Scrum Master would coach the team on improving their estimations and commitment to
  • CExtend the Sprint in order to complete the Sprint Backlog items.
  • DInform Peter that the projected completion date is not correct. The Development team would

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    12% (4)
  • D
    76% (26)

Explanation

Option D is correct because Scrum is built on transparency and empiricism - when actual velocity (15 points) differs significantly from the projection (21 points), the Product Owner has an obligation to update stakeholders with a revised completion date based on real data, not assumptions. Continuing to manage to an invalid forecast violates the Scrum value of transparency.

Why the distractors are wrong:

  • A is incomplete reasoning - while missing shippable Increments is a serious issue, simply noting the missed opportunity doesn't address the forecasting problem or Peter's stakeholder responsibilities.
  • B misplaces responsibility - the Scrum Master can coach, but the core issue here is not estimation accuracy, it's that Peter needs to reforecast based on the team's demonstrated capacity.
  • C directly violates Scrum - Sprint length is fixed for the duration of a project. Extending a Sprint to "finish the backlog" undermines the Sprint's time-box and hides the team's true velocity.

Memory tip: Think of the Product Owner as the forecast owner. Whenever real data (actual velocity) contradicts the plan, the PO must update the forecast - just like a navigator who adjusts the ETA when actual speed differs from estimated speed. "New data = new date."

Topics

#velocity#shippable increment#Product Owner#Sprint forecasting