Question

What activities would a Product Owner do during an active Sprint?

Options

  • AEngage with the stakeholders and answer questions from the Development Team.
  • BPrioritize the Sprint Backlog.
  • CParticipate at the Daily Scrum.
  • DUpdate the burndown chart.