Scrum
PSM-II · Question #62
PSM-II Question #62: Real Exam Question with Answer & Explanation
The correct answer is A. Engage with the stakeholders and answer questions from the Development Team.. See the full explanation below for the reasoning.
Question
What activities would a Product Owner do during an active Sprint?
Options
- AEngage with the stakeholders and answer questions from the Development Team.
- BPrioritize the Sprint Backlog.
- CParticipate at the Daily Scrum.
- DUpdate the burndown chart.
Community Discussion
No community discussion yet for this question.