PSM-II · Question #61

Who is responsible for ensuring the Product Backlog items are understood to the level needed?

The correct answer is D. The Product Owner. The Product Owner is accountable for managing the Product Backlog.

Applying Scrum

Question

Who is responsible for ensuring the Product Backlog items are understood to the level needed?

Options

  • AThe Business Analyst.
  • BThe Scrum Master.
  • CThe Development Team.
  • DThe Product Owner.

How the community answered

(54 responses)
  • A
    2% (1)
  • C
    4% (2)
  • D
    94% (51)

Explanation

The Product Owner is accountable for managing the Product Backlog.

Topics

#Product Owner#Product Backlog#accountability#Scrum roles