nerdexam
Scrum

PSM-II · Question #66

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

The correct answer is B. As much as it has informed the Product Owner will be done for every Product Backlog item it. Option B is correct because the Scrum framework requires the Development Team to meet its own Definition of Done for each Product Backlog item - the exact standard of "done" that has been communicated to the Product Owner. The team commits to completing each selected item fully…

Applying Scrum

Question

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

Options

  • AAn equal amount of time on analysis, design, programming, testing and documentation.
  • BAs much as it has informed the Product Owner will be done for every Product Backlog item it
  • CAll development work and at least some testing.
  • DAs much as it can fit into the Sprint. Any remaining work will be moved to a subsequent Sprint.

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    92% (34)
  • C
    3% (1)
  • D
    3% (1)

Explanation

Option B is correct because the Scrum framework requires the Development Team to meet its own Definition of Done for each Product Backlog item - the exact standard of "done" that has been communicated to the Product Owner. The team commits to completing each selected item fully to that agreed standard, not partially.

  • A is wrong because Scrum doesn't prescribe equal time allocation across activities. Teams self-organize and decide how to distribute effort based on what each item actually needs.
  • C is wrong because "all development work and at least some testing" implies testing can be incomplete, which violates the Definition of Done - testing must be fully completed to the agreed standard, not partially.
  • D is wrong because this describes scope spillover, which Scrum discourages. If a team can't complete an item to the Definition of Done within the Sprint, it should not be split across Sprints arbitrarily - incomplete items are returned to the Product Backlog.

Memory tip: Think of it as a promise to the Product Owner - the team selects items it can fully deliver to the standard it already told the PO, no more, no less. "Done means done as defined."

Topics

#Sprint commitment#Product Backlog items#Definition of Done#Sprint Planning

Community Discussion

No community discussion yet for this question.

Full PSM-II Practice