Who can cancel a Sprint? (Choose the best answer)

The correct answer is D. The Product Owner. According to the Scrum Guide, the Product Owner can cancel a Sprint, as he or she is responsible for maximizing the value of the product and the work of the Development Team. The other roles do not have this authority, although they may provide input and suggestions to the

Submitted by noor.lb· Apr 18, 2026Scrum Framework

Question

Who can cancel a Sprint? (Choose the best answer)

Options

  • AThe Scrum Master
  • BThe Scrum Team.
  • CThe Stakeholders.
  • DThe Product Owner.

How the community answered

(38 responses)
  • B
    5% (2)
  • C
    3% (1)
  • D
    92% (35)

Explanation

According to the Scrum Guide, the Product Owner can cancel a Sprint, as he or she is responsible for maximizing the value of the product and the work of the Development Team. The other roles do not have this authority, although they may provide input and suggestions to the