PSM-I · Question #106

What is the Sprint Backlog?

The correct answer is C. The Product Backlog items selected for this Sprint plus the plan for delivering them. The Sprint Backlog is defined in the Scrum Guide as the set of Product Backlog items selected for the Sprint, PLUS a plan for delivering them and realizing the Sprint Goal. It is not merely a list of selected items (D) - it must also include the delivery plan. This plan is…

Submitted by priya_blr· Apr 18, 2026Scrum Framework

Question

What is the Sprint Backlog?

Options

  • AThe plan for delivering Product Backlog items
  • BThe Product Backlog items selected for this Sprint plus the Team Backlog items
  • CThe Product Backlog items selected for this Sprint plus the plan for delivering them
  • DThe Product Backlog items selected for this Sprint

How the community answered

(27 responses)
  • A
    7% (2)
  • C
    89% (24)
  • D
    4% (1)

Explanation

The Sprint Backlog is defined in the Scrum Guide as the set of Product Backlog items selected for the Sprint, PLUS a plan for delivering them and realizing the Sprint Goal. It is not merely a list of selected items (D) - it must also include the delivery plan. This plan is typically a visible breakdown of tasks the Development Team uses to manage their work throughout the Sprint.