PSM-I Question #192: Real Exam Question with Answer & Explanation
The correct answer is B: The sum of all the Product Backlog items completed during the Sprint and the value of the. The Increment is the sum of all Product Backlog items completed during the Sprint plus the value of all previous Sprint Increments. This additive definition is critical: each new Increment builds on everything that came before it and must be in a usable, 'Done' condition. Option
Question
What is the Increment?
Options
- AAll "Done" items in the Sprint Backlog
- BThe sum of all the Product Backlog items completed during the Sprint and the value of the
- CAll items in the Sprint Backlog that could be released regardless of whether the Product Owner
- DThe sum of all the Product Backlog items completed during the Sprint
Explanation
The Increment is the sum of all Product Backlog items completed during the Sprint plus the value of all previous Sprint Increments. This additive definition is critical: each new Increment builds on everything that came before it and must be in a usable, 'Done' condition. Option A is wrong because 'Done' items in the Sprint Backlog alone do not account for prior increments. Option D is similarly incomplete because it omits previous Increments. Option C is wrong because releasability is the Product Owner's decision, not a defining characteristic of the Increment itself.