PSM-I · Question #191
PSM-I Question #191: Real Exam Question with Answer & Explanation
The correct answer is E: The Product Owner. The Product Owner alone owns and is accountable for the Product Backlog. This includes ordering items by value, ensuring the backlog is visible and transparent, and making sure the Development Team understands the items to the level needed. While the Development Team may contribu
Question
Who is responsible for the Product Backlog?
Options
- AThe Scrum Master and The Development Team
- BThe Product Owner and The Scrum Master
- CThe Product Owner and The Development Team
- DThe Scrum Master
- EThe Product Owner
- FThe Development Team
Explanation
The Product Owner alone owns and is accountable for the Product Backlog. This includes ordering items by value, ensuring the backlog is visible and transparent, and making sure the Development Team understands the items to the level needed. While the Development Team may contribute estimates and refinement input, and the Scrum Master may facilitate backlog refinement sessions, ultimate responsibility rests solely with the Product Owner.
Topics
Community Discussion
No community discussion yet for this question.