PSM-I · Question #271
Who is responsible for collaboration with stakeholders? (Choose the best answer)
The correct answer is B. The Scrum Team. In Scrum, the entire Scrum Team - Product Owner, Scrum Master, and Developers - is collectively responsible for collaborating with stakeholders. The Product Owner is the primary point of contact for stakeholder needs, but collaboration is a team-wide accountability. Choices A…
Question
Who is responsible for collaboration with stakeholders? (Choose the best answer)
Options
- AThe Business Analyst.
- BThe Scrum Team.
- CThe Team Manager.
- DThe Project Manager.
- EThe Developers.
How the community answered
(52 responses)- A4% (2)
- B92% (48)
- C2% (1)
- D2% (1)
Explanation
In Scrum, the entire Scrum Team - Product Owner, Scrum Master, and Developers - is collectively responsible for collaborating with stakeholders. The Product Owner is the primary point of contact for stakeholder needs, but collaboration is a team-wide accountability. Choices A (Business Analyst), C (Team Manager), and D (Project Manager) are not defined Scrum roles. Choice E (Developers alone) is too narrow, as it excludes the Product Owner and Scrum Master who are also key in stakeholder engagement.