PSM-I · Question #272

When multiple Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint? (Choose the best answer)

The correct answer is D. Yes, in order to accurately inspect what is done. According to the Scrum Guide, when multiple Scrum Teams are working on the same product, they should integrate their Increments every Sprint, in order to accurately inspect what is done and ensure that there is no technical debt or unfinished work at the end of each Sprint. The…

Submitted by renata2k· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

When multiple Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint? (Choose the best answer)

Options

  • AYes, but only for Scrum Teams whose work has dependencies.
  • BNo, that is tar too nard and must be done in a hardening Sprint
  • CNo, each Scrum Team stands alone.
  • DYes, in order to accurately inspect what is done.

How the community answered

(25 responses)
  • B
    4% (1)
  • C
    8% (2)
  • D
    88% (22)

Explanation

According to the Scrum Guide, when multiple Scrum Teams are working on the same product, they should integrate their Increments every Sprint, in order to accurately inspect what is done and ensure that there is no technical debt or unfinished work at the end of each Sprint. The other options are not valid, as they imply that integration can be skipped, delayed, or done only for some teams, which is not consistent with Scrum values and principles.