PSM-I · Question #79

Which best describes the Product Backlog?

The correct answer is A. It is allowed to grow and change as more is learned about the product and its customers. According to the Scrum Guide, the Product Backlog is an ordered list of everything that is known to be needed in the product. It is allowed to grow and change as more is learned about the product and its customers. The other options are not accurate descriptions of the Product…

Submitted by chen.hong· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Which best describes the Product Backlog?

Options

  • AIt is allowed to grow and change as more is learned about the product and its customers.
  • BIt provides just enough information to enable a Scrum team to start the design phase of a product.
  • CIt contains all foreseeable tasks and requirements from which the Scrum team can develop and
  • DIt is baselined to follow change management processes.

How the community answered

(22 responses)
  • A
    86% (19)
  • C
    5% (1)
  • D
    9% (2)

Explanation

According to the Scrum Guide, the Product Backlog is an ordered list of everything that is known to be needed in the product. It is allowed to grow and change as more is learned about the product and its customers. The other options are not accurate descriptions of the Product Backlog, as they are either too restrictive (such as providing just enough information or baselining to follow change management processes) or too comprehensive (such as containing all foreseeable tasks and requirements or enabling a complete project plan).

Topics

#Product Backlog#Empiricism#Adaptability#Product Backlog Refinement