PSM-I · Question #273

PSM-I Question #273: Real Exam Question with Answer & Explanation

The correct answer is B: When the Sprint Retrospective is complete.. According to the Scrum Guide, a Sprint concludes when the Sprint Retrospective is complete. This is the last event of the Sprint cycle, where the Scrum Team inspects itself and creates a plan for improvements. The other options are not valid indicators of the conclusion of a Spri

Submitted by kevin_r· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

When does a Sprint conclude? (Choose the best answer)

Options

  • AWhen the Product Owner decides enough has been delivered to meet the Sprint Goal.
  • BWhen the Sprint Retrospective is complete.
  • CWhen all the tasks are completed by the Developers.
  • DWhen all Product Backlog items meet their Definition of Done.

Explanation

According to the Scrum Guide, a Sprint concludes when the Sprint Retrospective is complete. This is the last event of the Sprint cycle, where the Scrum Team inspects itself and creates a plan for improvements. The other options are not valid indicators of the conclusion of a Sprint, as they are either irrelevant (such as the Product Owner deciding enough has been delivered) or incomplete (such as all tasks or Product Backlog items being done).

Topics

#Sprint Lifecycle#Scrum Events#Sprint Retrospective#Scrum Framework Basics

Community Discussion

No community discussion yet for this question.