The correct answer is B: When the Sprint Retrospective is complete.. According to the Scrum Guide, a Sprint concludes when the Sprint Retrospective is complete. This is the last event of the Sprint cycle, where the Scrum Team inspects itself and creates a plan for improvements. The other options are not valid indicators of the conclusion of a Spri
Question
When does a Sprint conclude? (Choose the best answer)
Options
- AWhen the Product Owner decides enough has been delivered to meet the Sprint Goal.
- BWhen the Sprint Retrospective is complete.
- CWhen all the tasks are completed by the Developers.
- DWhen all Product Backlog items meet their Definition of Done.
Explanation
According to the Scrum Guide, a Sprint concludes when the Sprint Retrospective is complete. This is the last event of the Sprint cycle, where the Scrum Team inspects itself and creates a plan for improvements. The other options are not valid indicators of the conclusion of a Sprint, as they are either irrelevant (such as the Product Owner deciding enough has been delivered) or incomplete (such as all tasks or Product Backlog items being done).