PSM-I · Question #270

True or False: The Product Owner makes sure the Developers select enough from the Product Backlog tor a Sprint to satisfy the stakeholders.

The correct answer is B. False. According to the Scrum Guide, the Product Owner does not make sure that the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Developers are responsible for selecting how much work they can do in a Sprint, based on their capacity…

Submitted by mike_84· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

True or False: The Product Owner makes sure the Developers select enough from the Product Backlog tor a Sprint to satisfy the stakeholders.

Options

  • ATrue
  • BFalse

How the community answered

(45 responses)
  • A
    7% (3)
  • B
    93% (42)

Explanation

According to the Scrum Guide, the Product Owner does not make sure that the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Developers are responsible for selecting how much work they can do in a Sprint, based on their capacity and past performance. The Product Owner may influence them by ordering and clarifying the Product Backlog items, but does not control their selection.

Topics

#Product Owner Role#Developers' Self-management#Sprint Planning#Scrum Roles