PSM-I · Question #193
Who is responsible for creation of the Definition of "Done"?
The correct answer is D. The Development Team. Per the 2017 Scrum Guide (which this question references), if the organization does not have a standard Definition of Done, the Development Team must define one appropriate for the product. It is the Development Team who determines what 'Done' means for the Increment they…
Question
Who is responsible for creation of the Definition of “Done”?
Options
- AThe Product Owner
- BThe Scrum Team
- CThe Scrum Master
- DThe Development Team
How the community answered
(44 responses)- A5% (2)
- B2% (1)
- C7% (3)
- D86% (38)
Explanation
Per the 2017 Scrum Guide (which this question references), if the organization does not have a standard Definition of Done, the Development Team must define one appropriate for the product. It is the Development Team who determines what 'Done' means for the Increment they build, because they are the ones doing the work and can best judge the quality criteria. The Product Owner and Scrum Master can provide input, but the responsibility for creating and maintaining it belongs to the Development Team.
Topics
Community Discussion
No community discussion yet for this question.