Select the two meetings in which people outside the Scrum Team are allowed to participate.

The correct answer is B. The Sprint Planning D. The Sprint Review. The Sprint Review (D) explicitly invites key stakeholders chosen by the Product Owner to inspect the Increment and provide feedback. Sprint Planning (B) allows the Scrum Team to invite domain experts or technical specialists if additional input is needed. The Daily Scrum (A) is…

Submitted by klara.se· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Select the two meetings in which people outside the Scrum Team are allowed to participate.

Options

  • AThe Daily Scrum
  • BThe Sprint Planning
  • CThe Sprint Retrospective
  • DThe Sprint Review

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    86% (24)
  • C
    4% (1)

Explanation

The Sprint Review (D) explicitly invites key stakeholders chosen by the Product Owner to inspect the Increment and provide feedback. Sprint Planning (B) allows the Scrum Team to invite domain experts or technical specialists if additional input is needed. The Daily Scrum (A) is restricted to the Development Team - others may observe but must not participate. The Sprint Retrospective (C) is an internal Scrum Team event and is intentionally closed to outsiders to promote candid reflection.

Topics

#Scrum Events#Event Participation#Stakeholders

Community Discussion