The correct answer is B: The Developers.. According to the Scrum Guide, the Developers are accountable for managing the progress of work during a Sprint, as they are responsible for creating a valuable Increment that meets the Definition of Done and the Sprint Goal. The other options are not valid, as they imply that the
Question
Who is accountable for managing the progress ot work during a Sprint? (Choose the best answer)
Options
- AThe Product Owner.
- BThe Developers.
- CThe Scrum Master.
- DThe most junior member ot the team.
Explanation
According to the Scrum Guide, the Developers are accountable for managing the progress of work during a Sprint, as they are responsible for creating a valuable Increment that meets the Definition of Done and the Sprint Goal. The other options are not valid, as they imply that the Product Owner, the Scrum Master, or the most junior member of the team are accountable for managing the progress of work, which is not consistent with Scrum.
Topics
Community Discussion
No community discussion yet for this question.