nerdexam
ScrumScrum

PSM-I · Question #277

PSM-I Question #277: Real Exam Question with Answer & Explanation

The correct answer is B: The Developers.. According to the Scrum Guide, the Developers are accountable for managing the progress of work during a Sprint, as they are responsible for creating a valuable Increment that meets the Definition of Done and the Sprint Goal. The other options are not valid, as they imply that the

Submitted by kavita_s· Apr 18, 2026Scrum Framework

Question

Who is accountable for managing the progress ot work during a Sprint? (Choose the best answer)

Options

  • AThe Product Owner.
  • BThe Developers.
  • CThe Scrum Master.
  • DThe most junior member ot the team.

Explanation

According to the Scrum Guide, the Developers are accountable for managing the progress of work during a Sprint, as they are responsible for creating a valuable Increment that meets the Definition of Done and the Sprint Goal. The other options are not valid, as they imply that the Product Owner, the Scrum Master, or the most junior member of the team are accountable for managing the progress of work, which is not consistent with Scrum.

Topics

#Developers#Accountabilities#Sprint progress#Self-management

Community Discussion

No community discussion yet for this question.

Full PSM-I PracticeBrowse All PSM-I Questions