PSM-I · Question #258
What is the timebox for a Sprint Planning event? (Choose the best answer)
The correct answer is B. 8 hours for a one-month Sprint. According to the Scrum Guide, the timebox for a Sprint Planning event is 8 hours for a one-month Sprint, proportionally shorter for shorter Sprints. The other options are not valid, as they are either too long (such as monthly), too vague (such as whenever it's done), or too…
Question
What is the timebox for a Sprint Planning event? (Choose the best answer)
Options
- AMonthly.
- B8 hours for a one-month Sprint
- CWhenever ills done
- D4 hours for a one-month Sprint
How the community answered
(30 responses)- A7% (2)
- B90% (27)
- D3% (1)
Explanation
According to the Scrum Guide, the timebox for a Sprint Planning event is 8 hours for a one-month Sprint, proportionally shorter for shorter Sprints. The other options are not valid, as they are either too long (such as monthly), too vague (such as whenever it's done), or too short (such as 4 hours for a one-month Sprint).