PSM-I · Question #168
PSM-I Question #168: Real Exam Question with Answer & Explanation
The correct answer is A: The Development Team after clarifying requirements with the Product Owner.. According to the Scrum Guide, Product Backlog refinement is an ongoing activity in which Product Backlog items are reviewed and revised. The Developers who will be doing the work are responsible for sizing or estimating it. The Product Owner may influence them by helping them und
Question
Who creates a Product Backlog Item's estimate?
Options
- AThe Development Team after clarifying requirements with the Product Owner.
- BThe Product Owner with input from the Development Team.
- CThe most senior people in the organization, including architects and subject matter experts.
- DThe Scrum Master.
- EThe Development Team, alone.
Explanation
According to the Scrum Guide, Product Backlog refinement is an ongoing activity in which Product Backlog items are reviewed and revised. The Developers who will be doing the work are responsible for sizing or estimating it. The Product Owner may influence them by helping them understand and select trade-offs.