PSM-I · Question #169

Who starts the Daily Scrum?

The correct answer is B. Whoever the Development Team decides should start. According to the Scrum Guide, during each Daily Scrum, each Developer answers three What did I do yesterday that helped meet our Sprint Goal? What will I do today to help meet our Do I see any impediment that prevents me or our Development Team from meeting our Sprint Goal? The…

Submitted by ricky.ec· Apr 18, 2026Scrum Framework

Question

Who starts the Daily Scrum?

Options

  • AThe person coming in last. This encourages people to be on time and helps to stay within the
  • BWhoever the Development Team decides should start.
  • CThe person who has the token.
  • DThe Scrum Master. This ensures that the Development Team has the meeting and stays within
  • EThe person who last broke the build.

How the community answered

(38 responses)
  • B
    89% (34)
  • C
    3% (1)
  • D
    3% (1)
  • E
    5% (2)

Explanation

According to the Scrum Guide, during each Daily Scrum, each Developer answers three What did I do yesterday that helped meet our Sprint Goal? What will I do today to help meet our Do I see any impediment that prevents me or our Development Team from meeting our Sprint Goal? The Developers can select whatever structure and techniques they want, as long as their Daily Scrum focuses on progress toward achieving their Sprint Goal and producing a usable Increment. The Developers can start with any one person and proceed in any order.

Topics

#Daily Scrum#Self-organization#Development Team#Scrum Events

Community Discussion