PSM-I · Question #268

user documentation is part ot your Definition ot Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do?…

The correct answer is A. The Developers on the Scrum Team should write the user documentatiom. According to the Scrum Guide, the Developers on the Scrum Team should write the user documentation, as they are responsible for creating a "Done" Increment that meets the Definition of Done and the Sprint Goal. The other options are not valid, as they imply that the user…

Submitted by fatima_kr· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

user documentation is part ot your Definition ot Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do? (Choose the best answer)

Options

  • AThe Developers on the Scrum Team should write the user documentatiom
  • BWait until you have a technical writer on your Scrum Team to take care of this.
  • CForm a separate team of technical writers that will work on an on-demand basis tor the various
  • DLet the user documentation remain undone and accumulate until after the last development Sprint.

How the community answered

(42 responses)
  • A
    71% (30)
  • B
    7% (3)
  • C
    5% (2)
  • D
    17% (7)

Explanation

According to the Scrum Guide, the Developers on the Scrum Team should write the user documentation, as they are responsible for creating a "Done" Increment that meets the Definition of Done and the Sprint Goal. The other options are not valid, as they imply that the user documentation can be deferred, ignored, or outsourced, which is not consistent with Scrum values and principles.

Topics

#Definition of Done#Self-managing teams#Cross-functional teams#Developer responsibilities

Community Discussion

No community discussion yet for this question.