PSM-I · Question #267
PSM-I Question #267: Real Exam Question with Answer & Explanation
The correct answer is C: The product has one Product Backlog.. When multiple Scrum Teams build one product, Scrum prescribes a single Product Backlog (C) managed by a single Product Owner (E). One Product Backlog ensures all teams work from the same prioritized list, enabling coherent product direction. One Product Owner ensures a unified vi
Question
You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product Select two conditions you should strive tor in this scenario. (Choose the best two answers)
Options
- AThere should be six Product Owners, one tor each Scrum Team.
- BThere should be six Product Owners, reporting to a Chief Product Owner.
- CThe product has one Product Backlog.
- DEach Scrum Team should have a separate Product Backlog.
- EThere should be only one Product Owner.
Explanation
When multiple Scrum Teams build one product, Scrum prescribes a single Product Backlog (C) managed by a single Product Owner (E). One Product Backlog ensures all teams work from the same prioritized list, enabling coherent product direction. One Product Owner ensures a unified vision and eliminates conflicting priorities between teams. Options A and B (six Product Owners or a hierarchy of Product Owners) are wrong because multiple Product Owners for a single product create conflicting priorities and governance complexity. Option D (separate backlogs per team) is wrong because it fragments the product vision and makes integration and prioritization across teams nearly impossible.