PSM-I · Question #266

How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning? (Choose the best answer)

The correct answer is B. as much as is required to meet the Scrum Team's Definition of Done. According to the Scrum Guide, the amount of work required of the Developers to complete a Product Backlog item selected during the Sprint Planning is as much as is required to meet the Scrum Team's Definition of Done. This means that the Developers must ensure that every item…

Submitted by hassan_iq· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning? (Choose the best answer)

Options

  • AAll development work and at least some testing.
  • Bas much as is required to meet the Scrum Team's Definition of Done.
  • CA proportional amount of time on analysis, design development and testing
  • DAs much as they can fit into the Sprint, with remaining work deferred to the next Sprint

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    86% (38)
  • C
    2% (1)
  • D
    9% (4)

Explanation

According to the Scrum Guide, the amount of work required of the Developers to complete a Product Backlog item selected during the Sprint Planning is as much as is required to meet the Scrum Team's Definition of Done. This means that the Developers must ensure that every item they work on is in a usable condition and meets all quality standards agreed upon by the team. The other options are not valid descriptions of the amount of work required, as they are either too vague (such as all development work and some testing or a proportional amount of time) or incorrect (such as fitting as much as possible or deferring work to the next Sprint).

Topics

#Definition of Done#Developers' Accountabilities#Product Backlog Item Completion#Sprint

Community Discussion

No community discussion yet for this question.