Question
When should a Sprint Goal be created?
Options
- AIt should have been created in the previous Sprint during Product Backlog refinement.
- BIt must be established before Sprint Planning in order to begin planning.
- CA Sprint Goal is not mandatory in Scrum.
- DAt any time during the Sprint.
- EDuring Sprint Planning.