PSM-I · Question #22
Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)
The correct answer is A. Identifying high priority process improvements for the next Sprint. C. How the team collaborates. According to the Scrum Guide, the purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. The Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done. Inspected…
Question
Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)
Options
- AIdentifying high priority process improvements for the next Sprint.
- BThe order of items in the Product Backlog.
- CHow the team collaborates.
- DDocumenting acceptance criteria for items in the next Sprint.
How the community answered
(30 responses)- A90% (27)
- B3% (1)
- D7% (2)
Explanation
According to the Scrum Guide, the purpose of the Sprint Retrospective is to plan ways to increase quality and effectiveness. The Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done. Inspected elements often vary with domain, practices, and people involved. The Scrum Team identifies the most helpful changes to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint. Therefore, two appropriate topics for discussion during a Sprint Retrospective are: Identifying high priority process improvements for the next Sprint. How the team collaborates. The other options are not relevant or appropriate for the Sprint Retrospective.