PSM-I · Question #21
PSM-I Question #21: Real Exam Question with Answer & Explanation
The correct answer is A: True. According to the Scrum Guide, the Sprint Goal is an objective set for the Sprint that can be met through the implementation of Product Backlog. It provides guidance to the Developers on why it is building the Increment. It also provides a basis for inspecting and adapting during
Question
The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.
Options
- ATrue
- BFalse
Explanation
According to the Scrum Guide, the Sprint Goal is an objective set for the Sprint that can be met through the implementation of Product Backlog. It provides guidance to the Developers on why it is building the Increment. It also provides a basis for inspecting and adapting during the Sprint Review and Sprint Retrospective. The Sprint Goal is a result of Sprint Planning, as is the Sprint