The correct answer is A: True. According to the Scrum Guide, the Sprint Goal is an objective set for the Sprint that can be met through the implementation of Product Backlog. It provides guidance to the Developers on why it is building the Increment. It also provides a basis for inspecting and adapting during

Submitted by olafpl· Apr 18, 2026Scrum Framework

Question

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.

Options

  • ATrue
  • BFalse

Explanation

According to the Scrum Guide, the Sprint Goal is an objective set for the Sprint that can be met through the implementation of Product Backlog. It provides guidance to the Developers on why it is building the Increment. It also provides a basis for inspecting and adapting during the Sprint Review and Sprint Retrospective. The Sprint Goal is a result of Sprint Planning, as is the Sprint

Topics

#Sprint Planning#Sprint Goal#Sprint Backlog#Scrum Artifacts

Community Discussion

No community discussion yet for this question.

Full PSM-I PracticeBrowse All PSM-I Questions