PSM-I · Question #24
PSM-I Question #24: Real Exam Question with Answer & Explanation
The correct answer is B: Coach the team on why the Daily Scrum is important as an opportunity to update the plan.. The correct answers are B and D, because these are the most appropriate responses for the Scrum Master. The Scrum Master should coach the team on why the Daily Scrum is important as an opportunity to update the plan, inspect the progress, and synchronize the activities of the Dev
Question
During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)
Options
- AConsider the request and decide on which days the Daily Scrum should occur.
- BCoach the team on why the Daily Scrum is important as an opportunity to update the plan.
- CHave the developers vote.
- DLearn why the Development Team wants this and work with them to improve the outcome of the
- EAcknowledge and support the self-organizing team's decision.
Explanation
The correct answers are B and D, because these are the most appropriate responses for the Scrum Master. The Scrum Master should coach the team on why the Daily Scrum is important as an opportunity to update the plan, inspect the progress, and synchronize the activities of the Development Team. The Scrum Master should also learn why the Development Team wants this and work with them to improve the outcome of the Daily Scrum, rather than imposing a decision or accepting their request without question.
Topics
Community Discussion
No community discussion yet for this question.